Park City Mountain opened its new Canyons Village Skyway on Nov. 19, replacing the open-air Cabriolet with an enclosed, 10-passenger gondola and completing a major piece of the resort’s multiyear arrival-area overhaul. The lift connects the lower village with the Canyons Village Forum and adds an intermediate stop serving guests staying between the two terminals.
More than 100 people attended the grand opening. The Skyway replaces a lift that transported guests for 26 years and will eventually connect directly with the new Canyons Village Parking Structure, which remains scheduled to open in early December. The gondola and garage are intended to improve the trip from putting on ski boots at the parking structure to reaching the village and slopes.
A 2,700-Foot Gondola With an Additional Stop
Built by Leitner-Poma of America, the Skyway spans approximately 2,700 feet and climbs nearly 200 vertical feet. The enclosed cabins accommodate up to 10 passengers and feature floor-to-ceiling windows and red leather seats.
The route largely follows the former Cabriolet corridor, with a new mid-station providing another place to board and unload. That stop expands the lift’s role within the village, giving nearby lodging guests and homeowners an intermediate connection to both the lower arrival area and the Forum.
The Skyway also uses a direct-drive system, which Leitner-Poma describes a high-torque, low-speed electric motor that directly turns the drive bullwheel, eliminating the traditional gearbox.
Park City Mountain’s published winter operating schedule lists Skyway service from 7 a.m. to 6 p.m., an 11-hour operating window. That begins two hours before the resort’s standard 9 a.m. ski lift opening and continues two hours beyond the usual 4 p.m. closing, although Skyway hours may change during special events.
Construction Followed the Cabriolet’s Retirement
The old Cabriolet made its final trips on March 29, ending a run that began in 2000. Crews broke ground on its replacement the following day, and the Skyway was making test laps in October ahead of its November debut.
Park City Mountain and the Canyons Resort Village Management Association collaborated on the project, which followed about three years of planning. CVMA representatives told KPCW that the organizations worked together on decisions ranging from the lift’s name to the appearance of its cabins.
The association’s approved fiscal 2026 budget included a $9.24 million allocation from real estate transfer assessment reserves for the gondola. KPCW reported that both partners declined to disclose the project’s total price, so the allocation does not establish the full construction cost.
Parking Structure Will Complete the Arrival Connection
The Skyway’s opening comes while work continues on the parking structure near the Frostwood Drive and Canyons Resort Drive roundabout. The garage is designed to consolidate parking near S.R. 224 and provide a covered arrival point with a direct connection to the gondola.
Park City Mountain’s original design announcement outlined vehicle entrances on two levels, an internal drop-off area, a ground-floor pedestrian plaza connecting with transit and enclosed glass escalators between levels. The resort’s current winter project description pairs those improvements with the Skyway’s connection to the Forum.
The garage is scheduled to open in early December, with access beginning once construction is complete. Until then, Surface Lots 2, 3 and 4 will provide free parking with shuttle or walking connections to the upper village. Those temporary lots are scheduled to close when the garage opens.
The resort has announced a $29 daily garage rate, with free parking after noon and designated free carpool areas for vehicles carrying four or more people, subject to available space. Limited free parking will also remain in the surface lot adjacent to the garage on a first-come, first-served basis.
Second New Gondola in Two Winters
The Skyway follows the Sunrise Gondola, which opened for the 2025-26 season, giving Park City Mountain a second new gondola in consecutive winters. The resort currently lists Nov. 25 as the start of its 2026-27 ski season, subject to weather and conditions.
Additional lift work is planned for the following winter. Vail Resorts has announced an eight-passenger Silverlode replacement and a six-passenger chairlift replacing Eagle and Eaglet, targeting completion ahead of the 2027-28 season, along with a full retrofit of Crescent.